Download Trane Performance Air Handlers Installation and Maintenance Manual
Transcript
Installation - Mechanical TCP Base Section Assembly with Turned-Up Floor 1. See Figure 11. Apply 4-inch x ¼-inch neoprene gasket to the full perimeter face of each shipping split section. 2. Join the two sections and secure with field-provided 5/8-inch flat washers and 5/8-inch x 2 ½inch grade 9 bolts through each of the six holes. 3. Apply a heavy bead of caulk to the inside of the U-channel. 4. Press U-channel down over upturned flanges with moderate pressure to ensure it is fully seated onto upturned flanges. The caulk will cure and act as an adhesive to hold U-channel in place, no fasteners are required. Figure 11. Upturned floor assembly Cap Floor Caulk Cap Caulk Floor Floor Floor Gasket Gasket 24 CAH-SVX01B-EN