1.2 GENERAL REQUIREMENTS I.
The specifications indicated in the Tender are minimum and the Bidder is required to
comply and quote for all equipment and services mentioned in the Tender.
II.
Bidder should be responsible for the overall integration of the Servers, Storage and the
integration with existing Backup solution at OIL Duliajan.
The scope of work will not be limited only to supply, installation, commissioning,
III.
testing and integration of servers, storage infrastructure, along with associated software,
peripherals and accessories. The bidder also needs to perform a complete system study and plan
for a seamless migration to the proposed hardware.
IV.
The production and development database servers to be migrated to UNIX systems. The
production database server should be configured for high availability in active-passive mode.
V.
The application and web servers to be migrated to virtual environment and all the virtual
servers should be configured in high availability mode.
VI.
There should be 4 numbers of Web Server instance and 2 numbers of application server
instance configured in virtual environment and 2 Nos. of general purpose servers.
VII. The central storage should be connected to all servers through redundant paths as per
requirement and proposed solution.
VIII. The bidder should also configure a NAS server to be accessed by end users (Approx.
2000).
IX.
Backup should be configured for the entire landscape with the existing backup solution.
X.
The bidder is required to provide training to three(3) OIL engineers on i) blade
technology, ii) Virtualization & virtualization management Software iii) storage, with reference
to the provided solution at the OEM facility for a minimum period of 1 week.
XI.
Acceptance testing as per criteria defined during project kick-off will be prime
responsibility of the bidder for successful completion of the project.
XII. The installation, commissioning, virtualization, data migration needs to be carried out by
OEM authorized experienced engineer only.
XIII. There must be comprehensive 3 years warranty. During which an OEM authorized
experienced engineer needs to be deputed onsite. The personnel should be able to maintain the
entire setup.
XIV. Critical spares must be kept onsite for any eventuality. The list of the spares to be kept
must be provided with the bid.
XV. Any other items required for implementation of the solution will be provided by the bidder.
XVI. All the necessary softwares & drivers for the entire solution should be provided on
original CD/DVD media.
Page 2 of 15