The project will now complete towards the end of November instead of the end of October! The reason for this is simple: The tasks are defined so that the second round of design is not started until the marketing study is completed. We have told the software that Task 2 is being done by someone who only works 20 hours per week and so it recalculated the ending date (remember: Duration * Units = Work) and adjusted the schedule of the other tasks that depend upon it. Is this new Task 2 completion time a problem? We won’t know until we assign the resources to the rest of the tasks. To simplify the tutorial as this software development effort goes through three similar design, code and test cycles, we will assign team members only to Tasks 1 through 10. As an exercise, you can recreate the project plan where this tutorial ends, continue assigning people to the second and third development cycles, and see the schedule effects of bringing other people onto the team. We will next assign people to Tasks 3 through 10. (Task 1 is still being held off for discussion later on in this tutorial.) Recall that we have one software architect (TM4), TM3 can program but only functions A, B, and C, and TM1 can program but at a slow rate. The decision, therefore, of which team member will do the design task (Task 3) is simple, TM4, and we will make that allocation. We have four programming tasks, 4 through 7, one involving function D (Task 7) that only TM4 can code so we will allocate TM4 to that task. Since TM1 is slow, we will assign Task 6 to that person and the other two to TM3. (Making all assignments at the 100% Units level for now.) Moving beyond the programmers, TM5 is our test designer and so is assigned Task 8, TM6 executes tests and so is assigned Task 9 and, finally, TM7 is assigned the user documentation writing in Task 10. Except for now having the names beside the task’s bars, the Gantt chart remains unchanged: 21