Multi-user Knowledge Space
Sam Carney
Appendix B
Discussion of Project Plan and Project Methodology
Project Schedule
The original project schedule (Table 1.1) had to be revised after it became clear that the
implementation of version 2 was going to take a lot longer than originally envisaged (the reasons for
this are documented in the implementation section). After this assessment was made a new plan was
created so that the project did not just float along and lose productivity. The new plan allocated more
time to the design and development of the system to reflect the changing nature of the project
compared to the original plan. In the plan some tasks were carried out at the same time as other tasks
as it was not be possible to complete certain tasks like systems evaluation over the Easter break.
Stage
Date
Objective
Milestone
1
30/09/2004
Submit Project Preference form
2
14/10/2004
3
22/10/2004
Discuss the project idea with
supervisor
Complete Aim and Minimum
Requirements form
4
23/10/2004 –
30/10/2004
Research into the context of the
problem
5
30/10/2004 –
10/11/2004
Evaluation of Cai’s system
Evaluation section
6
11/11/2004 –
26/11/2004
Requirements Capture
Finalized
requirements for
version 2 system
7
26/11/2004 –
09/12/2004
Write up of Mid-Project Report
Mid-project Report
8
10/12/2004
Submit Mid-Project Report
9
13/12/2004 –
22/12/2004
Research into how to implement the
system
10
03/01/2005 10/01/2005
Design of version 2 system
Design section for
the project.
11
22/01/2005 –
25/02/2005
Implementation of version 2
System built.
12
25/02/2005 –
01/03/2005
Write up Implementation section of
report
Implementation
section for project.
53