Chapter 7. Property Reference
task effortTask "Effort Task" {
effort 10d
allocate tux
}
}
7.119. startbuffer <percent>
startbuffer <percent>
Description
Specifies how much slack time you expect to have at the beginning of the
task. This information has no impact on the scheduling of the project. It is for
documentation purposes only.
Attributes
Name
percent
Type
Description
REAL
Percent slack of the
overall effort, duration
or length of the task.
Scenario Spec.
Yes
Context
task,
Inheritable
No
See also
duration, endbuffer, effort, length
project simple "Simple Project" "$Id" 2000-01-01 - 2000-01-20
resource tux1 "Tux1"
task t1 "Task1" {
start 2000-01-01
length 10d
# 20% of the working time of this task are marked as buffer at the
# beginning.
startbuffer 20
# An additional 10% of the working time of this task are marked as
# buffer at the end.
endbuffer 10.0
allocate tux1
}
# Generate a report that lists the start end end dates for the
# buffers.
htmltaskreport "Buffer.html" {