Download RETScreen Software Online User Manual
Transcript
RETScreen® Ground-Source Heat Pump Project Model The year-to-positive cash flow differs from the discounted payback indicator in that it considers the nominal value of future cash flows rather than the discounted value of future cash flows. Net Present Value - NPV The model calculates the net present value (NPV) of the project, which is the value of all future cash flows, discounted at the discount rate, in today's currency. NPV is thus calculated at a time 0 corresponding to the junction of the end of year 0 and the beginning of year 1. Under the NPV method, the present value of all cash inflows is compared against the present value of all cash outflows associated with an investment project. The difference between the present value of these cash flows, called the NPV, determines whether or not the project is generally a financially acceptable investment. Positive NPV values are an indicator of a potentially feasible project. In using the net present value method, it is necessary to choose a rate for discounting cash flows to present value. As a practical matter, organisations put much time and study into the choice of a discount rate. The model calculates the NPV using the cumulative after-tax cash flows. In cases where the user has selected not to conduct a tax analysis, the NPV calculated will be that of the pre-tax cash flows. Annual Life Cycle Savings The model calculates the annual life cycle savings (ALCS) which is the levelized nominal yearly savings having exactly the same life and net present value as the project. The annual life cycle savings are calculated using the net present value, the discount rate and the project life. Benefit-Cost (B-C) ratio The model calculates the net benefit-cost (B-C) ratio, which is the ratio of the net benefits to costs of the project. Net benefits represent the present value of annual revenues (or savings) less annual costs, while the cost is defined as the project equity. Ratios greater than 1 are indicative of profitable projects. The net benefit-cost (B-C) ratio, similar to the profitability index, leads to the same conclusion as the net present value indicator. Calculate GHG reduction cost? The user indicates by selecting from the drop-down list whether or not the project GHG emission reduction cost should be calculated. In order to calculate the true economic cost (not the financial cost) of GHG emission reductions, a number of other parameters such as the GHG emission reduction credit, debt ratio, etc. should be set to 0. In addition "Income tax analysis" should be set to "No" and other taxes should also be set to 0. This option is more applicable to economists as it requires a careful analysis of assumptions used. GHG emission reduction cost The model calculates the GHG emission reduction cost. The GHG emission reduction cost is calculated by dividing the annual life cycle savings (ALCS) of the project by the net GHG GSHP.69