RETScreen® Ground-Source Heat Pump Project Model
The year-to-positive cash flow differs from the discounted payback indicator in that it considers
the nominal value of future cash flows rather than the discounted value of future cash flows.
Net Present Value - NPV
The model calculates the net present value (NPV) of the project, which is the value of all future
cash flows, discounted at the discount rate, in today's currency. NPV is thus calculated at a time
0 corresponding to the junction of the end of year 0 and the beginning of year 1. Under the NPV
method, the present value of all cash inflows is compared against the present value of all cash
outflows associated with an investment project. The difference between the present value of
these cash flows, called the NPV, determines whether or not the project is generally a financially
acceptable investment. Positive NPV values are an indicator of a potentially feasible project. In
using the net present value method, it is necessary to choose a rate for discounting cash flows to
present value. As a practical matter, organisations put much time and study into the choice of a
discount rate. The model calculates the NPV using the cumulative after-tax cash flows. In cases
where the user has selected not to conduct a tax analysis, the NPV calculated will be that of the
pre-tax cash flows.
Annual Life Cycle Savings
The model calculates the annual life cycle savings (ALCS) which is the levelized nominal yearly
savings having exactly the same life and net present value as the project. The annual life cycle
savings are calculated using the net present value, the discount rate and the project life.
Benefit-Cost (B-C) ratio
The model calculates the net benefit-cost (B-C) ratio, which is the ratio of the net benefits to
costs of the project. Net benefits represent the present value of annual revenues (or savings) less
annual costs, while the cost is defined as the project equity.
Ratios greater than 1 are indicative of profitable projects. The net benefit-cost (B-C) ratio,
similar to the profitability index, leads to the same conclusion as the net present value indicator.
Calculate GHG reduction cost?
The user indicates by selecting from the drop-down list whether or not the project GHG emission
reduction cost should be calculated. In order to calculate the true economic cost (not the financial
cost) of GHG emission reductions, a number of other parameters such as the GHG emission
reduction credit, debt ratio, etc. should be set to 0. In addition "Income tax analysis" should be
set to "No" and other taxes should also be set to 0. This option is more applicable to economists
as it requires a careful analysis of assumptions used.
GHG emission reduction cost
The model calculates the GHG emission reduction cost. The GHG emission reduction cost is
calculated by dividing the annual life cycle savings (ALCS) of the project by the net GHG