STEPS TO FOLLOW A. Lateral Isolation Ensure that the structural floor is dry and free of obstacles, discontinuities, dust, etc. Along the perimeter of the slab, install lateral isolation with mineral wool to ensure a complete decoupling with respect to surrounding walls and structure (also islands like columns, ducting, etc.). The height must be up to the finishing level of the floor (see figure on left). B. CDM-ISO-FLOAT For correct installation of the panels, use the installation plan provided which clearly shows the individual panels and their reference numbers (as indicated in the factory on the panels). Lay the panels making sure to follow the sequence as indicated. Lateral Isolation CDM-ISO-FLOAT Figure 1: Installation of prefabricated CDM-ISO-FLOAT panels Page 2 of 4 CDM-ISO-FLOOR CDM Reutenbeek 9-11 BE-3090 Overijse Belgium noise & vibration control T: + 32-2-6877907 F: +32-2-6873552 E: [email protected] www.cdm.be