Where the collector is installed as part of the roof, the provision for thermal insulation should, if possible,
be the same standard as the surrounding construction.
v)
In addition, the roof construction and materials should be protected from exposure to excessive
temperatures through contact with the collector components.
w) All pipe work should be insulated to protect from temperature extremes and to prevent condensation.
Also, they should have identification markings (high temperature, flow/return), be located so as to prevent
or restrict occupant contact and not cause risk to materials adjacent to or in contact with pipe work.
x)
The solar heating system may require the provision of an additional water storage tank in the attic. In this
case, the roof should be designed to take the additional loading.
Figure 2 — Vertical and horizontal cross-section of a solar collector installed in an inclined roof