If an activity cannot be scheduled at any time without causing resource infeasibility, it is scheduled at its early start time, and the heuristic goes on to the next activity. After acceptance of a new schedule, the resource infeasibility number "ri" will be zero, unless one or more activities were impossible to schedule without infeasibility. If this happens, the user can examine the schedule, change durations, and ask For the heuristic again. In most cases, it is also desirable to free the start times of activities that were fixed by earlier acceptance of a heuristic before asking for another, especially those activities that are closely related to an un-schedulable activity, either by successorship or- quasisuccessorship or competition for the same resources.