Download App B Sampling and Analysis Plan

Transcript
Project-Specific SAP for the Remedial Action
Installation Restoration Site 25
Former Naval Air Station Moffett Field, California
Sampling and Analysis Plan
Revision number: NA
Revision Date: NA
SAP Worksheet #1 — Title and Approval Page
FINAL
SAMPLING AND ANALYIS PLAN
(Field Sampling Plan and Quality Assurance Project Plan)
Remedial Action, Installation Restoration Site 25
Former Naval Air Station Moffett Field, California
January 2012
Prepared for:
Base Realignment and Closure Program Management Office West
1455 Frazee Road, Suite 900
San Diego, California 92108-4310
Prepared by:
ITSI Gilbane Company
2730 Shadelands Drive
Walnut Creek, California 94598
(925) 946-3100
Document Control Number: ITSI-0808-0003-0005
PreparedN62473-10-D-0808
under:
Contract Number
Contract Task Order CTO 0003
Prepared by:
Approved by:
rrsiGlsa
1/17/2012
Richard Flynn
Program Chemist, ITSI Gilbane
Date
Joseph Michalowski, Ph.D., C.H.M.M.
Acting Quality Assurance Officer
U.S. Navy, NAVFAC SW
Date
Page 1