(v) Preparation of Package Design including Single Line Diagrams with Design data and
typical installation detailing to specific equipments to clarify and guide the overall work
package to its equipment level.
(vi) DCTP shall review the building infrastructure availability and recommend necessary
suggestion & features incorporation in the design to meet overall DC design
requirements.
(vii) Schematic diagrams for various sub-systems.
(viii) Preparation of working drawings for the complete DC facilities.
(ix) Provide all technical assistance related to electrical liaising work.
(x) DCTP to provide self approved schedule of Quantities/ Bill of material to IITM which
should be as per IITM approved design drawings documents.
(xi) Integrate architectural & engineering features related to Data Centre in accordance with
established design criterion
(xii) Site Infrastructure Requirement / Report
(xiii) Preparing Data Centre Coordinated Layout
Deliverables
DCTP shall submit the following deliverables:(i) Coordinated Design Drawings
(ii) Coordinated Data Centre Layout document for all the work/Sub-Work Packages services
(iii) Schedule of quantities/Bill of material document for all Work/Sub-Work Packages
(iv) Product Specification Document for all Work/Sub Work Packages
(v) Product Make/Model with Capacity sizing calculation document for all work/Sub-Work
packages
(vi) Electrical SLD (up to Rack Level), Schematics, equipment design drawing document
(vii) Breakers tripping end to end coordination design and scheme
(viii) Air-conditioning cooling solution design
(ix) Air-conditioning solution Schematic and drawing documents
(x) Safety & Security and Building Management Schematic and drawings
(xii) Civil- DC architectural layout, Floor Loading Details, DC elevation and Sectional Drawing
(xiii) BMS Data Point summary document
All the above mentioned deliverables is applicable for each Work packages/Sub-Work
Packages and document shall be submitted as each package wise.
Completion Criteria
Submission of the above listed deliverables and respective approval IITM project In charge
or his designated representative constitutes the completion of this activity.
Completion Timelines
The activity should be completed before 100 days after signing the contract.
Material Ordering and Pre-Dispatch Inspection
Scope of Services
This shall comprise of
IITM’s HPC DATA CENTER RFP