SECTION 270528 - PATHWAYS FOR COMMUNICATIONS SYSTEMS
PART 1 - GENERAL
1.1
GENERAL REQUIREMENTS
A.
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
B.
Applicable requirements of Division 27 Communications shall be considered a part of this
section.
C.
This specification describes the products and execution requirements relating to Pathways for
Communications Systems.
1.2
SUBMITTALS
A.
1.3
Provide product data.
WORK INCLUDED
A. The work included under this Specification consists of furnishing all labor, equipment, materials,
supplies and performing all operations necessary to complete the installation. The Contractor will
provide and install all of the required material whether specifically addressed in the technical
specifications or not.
B. The work shall include, but not be limited to the following:
1.
Furnish and install complete Conduit System.
2.
Furnish and install all Telecommunications Outlet Boxes.
3.
Furnish and install all Pull Boxes.
4.
Furnish and install complete Cable Tray System.
5.
Furnish and install all Cable Hangers.
6.
Furnish and install all Velcro Straps.
PART 2 - PRODUCTS
2.1
APPROVED PRODUCTS
A.
Rigid/Intermediate Conduit manufacturer(s)
1.
Allied
2.
Triangle
3.
Wheatland
4.
Youngstown
B.
Non-Metallic (PVC) manufacturer(s):
1.
Carlon
2.
Georgia Pipe Company
3.
Or Approved Equal
C.
Electrical Metallic Tubing (EMT) manufacturer(s):
1.
Allied
2.
Triangle
3.
Wheatland
4.
Youngstown
Februray 7, 2014
PATHWAYS FOR COMMUNICATIONS SYSTEMS
270528 - 1