Download sequent p&d installation - IMPCO
Transcript
7) Apply some clean engine oil to the OEM injector o-rings and install the OEM fuel injector rails torqueing the bolts to OEM specifications. Intake manifold with OEM fuel injector rails installed and Sequent fuel hoses routed correctly. 8) Drill and tap the upper intake manifold for the brass vacuum port adapter using the 5mm drill and the 6mm tap. Clean all traces of metal chips from the manifold. Apply a light coat of Loxeal to the adapter threads before installing. Set the upper manifold aside in a clean area protected from dirt and debris. Cover the lower manifold to keep dirt and debris from entering the intake runners. D. Zenith Regulator and Coolant Hose Installation: 1) The Zenith Regulator will be installed in the center of the bulkhead utilizing three existing studs. ©2009 IMPCO Technologies, Inc. -13- 2009 3.5/3.9L Impala CNG