10. First start-up
General information
Please note!
The Sanyo CO2 Eco can be connected and started without the room
sensor and current sensors or heat pump being installed.
The room sensor is always recommended to be installed.
If the current sensors are chosen not to be installed, the internal
sequence steps of the electrical heater will not be optimized.
IMPORTANT: Before starting up the heat pump system (Heat Pump “YES” in menu
settings), be sure to water fill the heat pump pipe system to avoid the load circulation to
run dry.
Before the first start-up
1. Check that the product and the system are filled with water and the air is
taken out of the radiator system.
2.Check that all the hydraulic connections are sealed and have no leakage.
4.Check that sensors, radiator pump etc. are connected to the electricity.
First start
1. Turn the main switch on and the display lightens up.
2. To prevent damages on the product the control system asks if the system
has been filled up with water. Press the RESET button to confirm. This
sequence is taking place at every start up at the first operating hour of the
product.
3. Now the boiler starts to operate according to the manufacturing settings.
Main manufacturing settings:
- operation without room sensor
- operation without heat pump unit
- operation without temperature decrease during nights
4. If the heat pump unit is properly installed, water filled and conected, be assolutely
sure to conduct the ”Test Run”(described bellow). Then change the factory settings
according to the actual system requirements and customers demands.
Note: if the heat pump is not power connected, the boiler will display communication error.
Test run
(1) Turn on the power: Be absolutely sure to provide the adequate voltage.
(2) Operate the heat pump unit
① Press the OK button on the “Main menu display” to display the menus choice.
② Press the ▼ button twice to select “SETTING,” and then press the OK button to access.
③ Press the ▼ button once, to make the first row active to be changed. Then check that
“LANGUAGE” blinks.
④ Press once the OK button to step down and make “HEAT PUMP” active to be changed.
⑤ Press the ▲ button once to change “NO” to “YES.”
⑥ Check that the HP unit starts operating within 3 minutes.
A) Proceed to (3) if the HP unit has started operating.
B) If the HP unit fails to start operating within 3 minutes, press the Step back button several
times to return to the “Main menu display.
” If “COMM ERROR” appears on the display at this time, it means that there is something
wrong in the wiring connections. Be absolutely sure to turn off the power, and then refer to
“08. Electric installation” and recheck the wiring connections.
(3) Stop the heat pump unit operation
① Press the Step back button twice to return to the “MENUS” display.
53