3.4 UPS cabinet installation UPS cabinets must be permanently bolted or welded to the floor using the shipping brackets. Note! UPS cabinets can fall over if the shipping brackets are not used. Both rear and front shipping brackets must be used to secure the UPS cabinet to the floor. 3.5 Unloading the Battery Cabinet from the Pallet The battery cabinet is bolted to a pallet consisting of four angle metal supports secured to two four-inch by six-inch wood supports. 1. Unfasten front door latch and swing doors open. 2. Remove doors. Remove the retaining screw located inside each door at the bottom hinge pivot point, then lift the door off. Save the retaining screws for reinstallation of the doors. 3. Locate the field kit (packed inside of the cabinet). Locate the four 1/2I jacking bolts and install them in the threaded holes in the front and rear supports. Place a floor protector underneath each jacking bolt, and screw the bolts down against them. The floor protectors protect the floor from being marred by the jacking bolts. Figure 5. Removing Shipping Supports 4. Loosen, but do not remove, the hardware holding the 4×6 supports to the front and rear supports. 1023294 Revision C UPS 40 – 160 kVA, 400V 50/60 Hz output User’s and Installation Guide 13