o
Room Information (Room Areas, People and Lighting Densities, Temp
space Set-points, Ventilation and airflow info)
System Information (Airside system information, cooling and heating
supply temps, control schemes like supply temp reset, fan information)
Room Assignment Tree (Which rooms are assigned to what system)
Plant Information (Equipment types and efficiencies, chilled and hot water
resets)
Economic Information (Costs, study life, tax rates, inflation rates, first
costs, maintenance costs)
Library Members (All the libraries that were used in the file would come
from here; for example, wall construction, people and lighting schedules,
equipment information, utility rates)
Walls by Direction (Areas of walls, glass area and U-factors, overhangs,
and shading)
Trace Outputs:



Monthly Energy Consumption (Total Monthly Electric and Gas
Consumption)
Equipment Energy Consumption (Total Monthly Electric and Gas
Consumption of each piece of equipment, including lighting and misc.
loads)
Economic Summary (Total costs comparisons)
Program staff will review the modeling files to verify that the baseline inputs meet the baseline
requirements described in these Technical Guidelines and to confirm that the energy savings
estimates are accurate and reasonable. If the inputs or resulting estimates do not appear to
meet Program requirements, the Program may require a revised analysis or request additional
information. Energy Trust's review is for Program purposes only, so we can clearly understand
the scope of the project, proposed EEMs, and source of the energy savings and confirm
whether or not proposed EEMs appear to be eligible for Energy Trust incentive funding. Final
determination of whether EEMs are eligible for Program incentives rests with Energy Trust.