FRONT MATTER
EC 9852
Quick Start Guide.
Step 1 – Installation:
•
•
•
•
•
•
•
Inspect analyzer for damage before turning on.
Service Manual:- 1.1.
Select an appropriate location.
Operation Manual:- 2.1.1.
Connect Gas lines.
Operation Manual:- 2.1.2.2.
Connect Analog Output Cables.
Operation Manual:-2.1.2.1.
Connect RS232 Cables.
Operation Manual:- 4.2.1.
Check the mains power selection switch (115 or 230 VAC).Operation Manual:- 2.2.
Connect AC Mains Power.
Operation Manual:- 2.2.
Step 2 – Start-up:
•
•
•
•
•
Set Service Switches.
Service Manual:- 1.1.2.
Turn On power.
Operation Manual:- 2.2.
The Display should read “9852 Analyzer”.
Adjust the Display Contrast if required.
Operation Manual:- 2.2.1.
Verify that the software is running by observing the Ecotech Globe rotating in the bottom
left hand corner of the display.
Step 3. – Operation:
•
•
•
•
•
Verify Instrument warm up and operation mode.
Set the correct time and date.
If using RS232, configure the Interface menu.
Check SYSTEM FAULTS menu. All PASS.
Verify other menu settings.
Service Manual:- 2.2.
Operation Manual:- 2.3.3.
Operation Manual:- 2.5.12.
Operation Manual:- 2.5.21.
Service Manual:- 4.2.
Step 4. – Calibration:
•
•
•
•
•
Perform a quick (single point) calibration.
Setup and Calibrate the Analog Outputs (if applicable).
If necessary, perform a leak check.
If necessary, perform a flow calibration.
If necessary, perform a Multipoint calibration.
Operation Manual:- 2.4.
Operation Manual:- 2.6.3.
Service Manual:- 3.3.13.
Service Manual:- 3.5.
Operation Manual:-3.4.
Step 5. – Data Validation:
•
•
Verify the results from your data acquisition system agree with the readings of the
EC9852 Sulfur Compound analyzer.
Verify that the analyzer responds to automatic calibration sequences.
The analyzer is now operating correctly.