Figure 4: Corner reinforcement brackets or angle
bars to be removed from the split section. Reset
the screws with rubber washer in place for watertightness.
IMPORTANT
Make sure to have full contact between strips wherever a
discontinuity is present, for air- and water-tightness.
Figure 5a: Install a polyvinyl gasket strip on each
vertical outside wall ¼” [6.4 mm] from the outside
side edge from top to bottom of the side joint. When
compressed, a small gap will remain which will allow
the Adseal 1800 series silicone-based sealant or
equivalent to seal the vertical side edges (explained in
Figure 7c).
¼”
Polyvinyl 30100
FLD + 900
½” x 1½” x 25”
Figure 5b: Install two horizontal polyvinyl gasket strips
along the base frame, one at the top and one at the
bottom of the base frame between the two vertical
side gasket strips so there is full contact between
gasket strips for air- and water-tightness.
Top of frame
5. Verify that these two sections are aligned square at
the joint in all three directions.
6. Install the ½” x 1½” [13 x 38 mm] polyvinyl gasket
with adhesive strip directly on one side of the split
section perimeter frames and middle interior partitions as shown in Figure 5a through Figure 5d.
Figure 5: General gasket layout
Bottom of frame
5a, 5c
5d, 5e
5b