4
• No risks if used on high pressure or flammable fluids pipelines. (gas and oil pipelines,
propane pipelines, etc).
• No risks if used on pipelines where thickness loss is confirmed or to be confirmed, cases
where conventional welding would be extremely dangerous.
• Being a cold system, special permissions to decrease pressure on the pipelines are not
necessary, which most of the times is not posible.
• Low installation difficulty.
• High electrical conductivity. The suggested nominal value for the welding is 30 Amps, if it is
necessary to drain higher currents, can be distributed on several weldings.
• Once the system is installed and the curing times are properly observed, can be considered
as a metallic fill with good structure, and it is for this reason that high values of current can
be drained. As regards as peak values that go over the current nominal value (30 A) whose
duration remains under 1 second, the product endures those peaks without any
inconvenience. Numerous products already installed in diverse working conditions haven’t
reported failures or fractures caused by high drains of current.
Installation.
A cold welding installation can be performed easily, in compliance with instructions and easy
considerations, which are also common to general welding or coating type of work. The skills
required to the staff that will apply the product will be minimum, althought will need to have
general electricity knowledges, as well as surface preparation, use of manual tools and detailed
way of work.
Verification of components.
Before execute the work, verify that it is at your hand all the hended tools to perform the welding,
this incluyes the tools provided with the Kit, in addition to other necessary tools on every welding
work (file, sandpaper, cloth, usual hand tools, etc.).
Do not use the Kit materials if you notice any failure or burst on it.Surface preparation.( in agree
with SSPC Standards: SP-2 and / or SP-3)
Clean the surroundings of the pipe or surface where the welding is going to be located, clearing it
from any remainder of dirt, grease, dust and old rust, paint, and soak through the coating until
reaching the metal. The surface should be 5cm x 5cm.
Clean and prepare the metallic zone by using files or sandpapers, until observe the metal clearly
clean, without any remainder of rust, adhesives or coating materials.
PROTAN S.A. – Catamarca St # 1207 – Zip: (2134) – Roldan City -