Download User Guide - Scope Safety Systems

Transcript
User Guide
Beam Rail(J-Bar Off Channel)
Note: - Maximum Post spacing is 3000mm.
- Installer must manage working at heights in
accordance with state legislation under the
OH+S act.
Rails
2D Post
(CR0200)
Channel Bar-J
(CR0060)
G-Clamp
(CR0010)
Standard Beam
Bottom Post
(CR0180)
Step – 1
Step – 2
Position the G-clamp on to channel.
Slide the J bar into G-clamp and tighten wing bolt.
Ensureing J-Bar is hard up against back face off
beam.
User Guide
Beam Rail(J-Bar Off Channel)
Step – 3
Step - 4
Slide Bottom post onto the J-Bar and tighten the
wing bolt.
Slide the 2D post into the Bottom Post and tighten
the wing bolt with 'D's facing towards working area.
Step – 5
Slide the rails into 2D post and tighten the L Bolt.
Mid rail