Download NetScreen-ISG 2000 User's Guide

Transcript
ISG 2000 Hardware Installation and Configuration Guide
To connect DC power-feed wires to the terminal block:
1. To open the three connectors on the terminal block so that they can receive
wire feeds, use the number-2 phillips screwdriver to turn the retaining screws
counterclockwise.
Figure 17: Opening the Connectors
Grounding wire
Positive
voltage
wire
(red)
Negative
voltage
wire
(black)
2. Insert a 0V DC (positive voltage) return wire into the center COM connector and
a -48V DC power-feed wire into either the left or the right connector.
3. Fasten the screws over the connectors.
4. Press the power switch to the ON position.
NOTE:
54
„
Power Supply Units
If both PSUs are installed and either of them is off, the ALARM LED on the front
panel glows red. This warning indicates that maximum device reliability requires
all installed PSUs to be operational.