Closing permits – Unmanned Sites
When the site is not manned and the permit is fully approved and printed, the
following persons will be able to close permits for their own company:
• All requestors from the company doing the work
• Competent person from the company doing the work on the permit
• Issuer(s)
Requestors from the Company doing the work and the CP will not be able to
issue, Isolation permits from other Companies associated with their permits.
When the site is not manned and the Isolation permit is fully approved and
printed, the following person(s) will see the approved isolation permits for their
attention and be able to close
• All the requestors from the companies performing the isolations
• The competent person on the permit from the companies performing the
isolations
• Issuers
The system should then be updated to reflect that the physical permit has been
closed. By selecting open permits (1) for your attention within the e-permits today
page it will display the permits for closure.
They should be closed in sequence starting with the high-risk permits.
Clicking on
will display a summary of the Task and allow you to log
whether the work was completed and whether the work was done safely. If it
was, set both selections to yes and click
.