Note: The picture above shows a snapshot from an activity list when using the "Fixed duration" project method. The
differences between the two project methods are covered in the "Fixed work and fixed duration" section of this
manual.
Tip: Proceed to the Working with the timeline view section of this help manual to learn more about working with
visualized activities.
Changing the activity name
Double-click on a task in the "activity name" column and write or change the name of the task. You can also
change the activity name in the activity details window, located below the timeline list.
Setting the start or finish date
Double clicking on a date allows it to be set. How dates are entered is selected in My personal Option under Editing.