Download User Manual

Transcript
RLT Instrumentation Pvt Ltd
(Unit of RLT Group)
Noisy Process
Chemical additives upstream
of magnetic flow meter.
Move injection point downstream of
magnetic flow meter, or move magnetic
flow meter.
Sludge flows–
Mining/Coal/Sand/
Slurries (other slurries with
hard particles).
Decrease flow rate below 10 ft/s.
Consult factory.
Styrofoam or other insulating
particles in process.
Use replaceable electrodes
Downsize flowtube to increase flow rate
above 3 ft/s. Periodically clean
flowtube.
Electrode coating.
Move the flowtube to another location
in the process line to ensure that it is full
under all conditions.
Air in line.
Meter output is
unstable.
Electrode incompatibility.
Check Magnetic Flow meter Material
Selection Guide for chemical
compatibility with electrode material.
Check ground wiring. See wiring and
grounding procedures.
Improper grounding.
Move magnetic Flowmeter (20–25 ft.
away is usually acceptable).
High local magnetic or electric
fieKF-700s.
Control loop improperly tuned.
Sticky valve (look for periodic
Oscillation of meter output).
Flowtube failure.
Check control loop tuning.
Correct valve sticking.
Perform Flowtube Tests.
Check that the 4–20 mA loop matches
the digital value. Perform loop test.
Analog output loop problem.
29
People are our prime movers