SECTION A4
DRAWINGS AND MANUALS
A4.1
DRAWINGS IN ELECTRONIC FORMAT
The Contractor shall provide drawings in electronic format as required in the
following clauses. These drawings shall conform to the latest version of CAD
Standard of Works Projects (CSWP) as posted in the website of the Works
Branch, Development Bureau and in accordance with the latest version of CAD
Manual for Architectural Services Department Projects. Should any technical
conflict between the CSWP and the CAD Manual arise, the CSWP shall take
precedence.
A4.2
INSTALLATION DRAWINGS
Drawing Submission Schedule
ft
A4.2.1
The Contractor shall submit a detailed installation drawing submission
schedule and programme to the Architect. The Contractor shall allow
reasonable time in the programme for vetting of the installation
drawings by the Architect and for drawing resubmissions as necessary.
D
ra
The Contractor shall submit to the Architect a comprehensive
“Submission Schedule” of installation drawings and builder‟s work
drawings within 2 weeks after the acceptance of Tender, taking into
account of the overall programme of the Works including any
Specialist Works and works by the utility undertakings. No equipment
shall be delivered to the Site and no works shall be executed until the
installation drawings have been approved by the Architect. The
Contractor shall ensure that installation drawings and builder‟s work
drawings are progressively submitted in accordance with the approved
“Submission Schedule”.
The Contractor shall provide at least 6 hard copies and one electronic
copy, unless otherwise specified in the Contract, of the approved
installation drawings to the Architect for distribution.
Section A4
Page 1 of 10
BRI_GS
2012 Edition