7
Figure 60: Replacing Pass
Two passes will be created, Pass 2 and Pass 3.
Pass 2: Reversing Pass (original pass number). This pass will cancel the dimensions and
values of the original pass by assigning a negative number to the quantity. In this case,
the Quantity will be -1.
Pass 3: Replacing Pass (original pass number). The replacing pass takes the place of the
original pass in the estimate. In the example above, the new pass, which is labeled
number 3, replaces the original pass, which is labeled number 1.
7. Click OK to change the estimate.
If the above steps are not followed, the new pass values will be added to the
original estimate total. As a result, the estimate cost will include both totals.
Revising Data on the Spreadsheet
After completing the takeoff process (using Assembly, Item or Quick Takeoff), the items
selected appear on the estimate spreadsheet.