ESTIMATING FACTORS FOR THE NATIONAL PARK SERVICE (ADD-ONS)
Before beginning the steps to complete a Cost Estimate, a discussion of add-ons below will
serve as an introduction to explain variables that affect pricing projects.
Add-ons are assumptive conditions that drive costs for cost estimated projects. In the
NPS, there are five different factors that must be considered when developing a cost
estimate for a particular project. These factors must be added on to the estimate to
ensure that an estimate is as accurate as possible.
The following list identifies the estimating factors that will influence the cost data. NPS
estimating factors will default automatically to settings identified below; the percentage can
be adjusted manually, if conditions warrant.
•
•
•
•
•
Historic Preservation Factor (variable 0-100%, defaults to 0%)
Design Contingency (variable 0-20%, defaults to 20%)
Overhead (variable 0-20%, defaults to 15%)
Profit (variable 0-20%, defaults to 12%)
General & Administrative [a.k.a. General Requirements] (variable 4-20%, defaults to
15%)
Historic Preservation Factor defaults to 0%, but can be increased up to 100%,
dependent upon the level of historic techniques and materials required.
Design contingency is discussed earlier in this chapter. For a Class C estimate, design
contingency defaults to 20%. The CESS program automatically factors design
contingency into the cost estimate. For projects using existing design, this factor may be
reduced.
Overhead are the costs that a contractor has for doing business. A general contractor
has expenses not directly related to the construction of a project but which are vital to the
contractor’s business operations. These include fixed overhead (Federal and State
Unemployment costs, Social Security Tax, Builder’s Risk Insurance and Public Liability
Costs) and variable overhead (Worker’s Compensation Insurance, Main Office Overhead,
etc.). In CESS, overhead costs default to 15%. It may adjust up to 20% or down to 0%.
Profit percentage is variable on the size of the job and a contractor’s annual billing.
Contractors generally take more profit on a smaller job. However, in CESS, profit defaults
to 12% and may be adjusted up to 20% or down to 0%.
General & Administrative (a.k.a., general requirements) are the costs to the
government from the contractor that are the cost items defined in the Division 1
specifications for a project. Sometimes some Division 1 items (Profit, Overhead) are
included in the cost of individual bid items when preparing an estimate. The following