6.3.1 Planning of Phase D As this CDR report marks the end of phase C (“Detailed Definition”), phase D (“Production/Ground Qualification Testing”) can be begun. It includes the assembly steps, in particular assembly on the clean bench that has to be prebooked. The team has decided to assemble parts that might be harmed by contamination as late as possible to avoid any needs of special storage. The main testing campaign is planned mid-September using the IRF space simulator (subject to pre-booking). Note that the different parts themselves are already tested before, individually. This is also to assure that they match the expected quality (e.g. the pump performance) and to be able to return them if need arises. 6.3.2 Important Dates • April 14th, 2008: PDR deadline (ESA) • May 8th: PDR deadline (IRV) • May 26th: CDR deadline (IRV) • June 2nd: CDR deadline (ESA) • June 15th: End of the semester at IRV • July 28th: MTR • September 8th: EAR • Flight Readiness Review: September 23 • October 4 - October 10: Launch campaign • January 15th, 2009: Experiment reported handed in at ESA 6.3.3 Mission Phases The Stratospheric Census Project is divided into the following phases: • Production and Testing Phase: The members of the team program and assemble the experiment at IRV in Kiruna, Sweden. • Mission Phase: The actual flight campaign in October 2008 • Recovery Phase: The filter has to be recovered for analysis. This is handled by Esrange. 60