The subprocess begins at node 1.
If node 2 finds that encumbrance is on and funds are not yet reserved,
node 4 attempts to reserve funds for the document.
If funds cannot be reserved, node 6 sends an Unable to Reserve
Document notification to the approver. The approver must then use the
Approve Document window to try to reserve the document again if,
for example, more funds have been allocated, and then respond to the
notification with Retry; reject the document; or forward the document
to somebody else with approval authority to reserve the funds.
If the approver forwards the document, node 7 checks if the
forward–to approver has a valid user name. If so, node 8 sets the
Forward–To/From information for the new approver.
If the approver rejects the document, node 9 rejects the purchase order.
If it cannot reject the purchase order (because the document failed the
state check—for example, its status has changed to closed, frozen, or on
hold), node 11 sends a notification to the approver that the document
could not be rejected.
If the Document Approval Manager fails at node 4 or 9, the notification
activity at node 5 or 10 sends a notification of the failure to the
Procurement Workflows C – 197