Download Section 1 - Community Transit

Transcript
REQUEST FOR PROPOSALS - RFP #50-07
ADVANCED PUBLIC TRANSPORTATION SYSTEM (APTS) PROCUREMENT
SECTION 3.0 - PAGE 8
Explosions, Collapse and Underground Hazards (Where Applicable)
Products/Completed Operations
Contractual Liability
Broad Form Property Damage
Independent Contractors
Personal Injury/Advertising Liability
Stop Gap Liability ($1,000,000 per person/$1,000,000 per occurrence)
Profession Services, Errors and Omissions ($1,000,000 per occurrence)
2.
Comprehensive auto liability in the amount of $1,000,000 per occurrence limit
which provides the following coverages:
Owned Vehicles
Nonowned Vehicles
Hired Vehicles
Deductibles and Self Insured retainers, if any, shall be identified in the Proposal.
All deductible payments are the responsibility of Contractor. The minimum
deductible shall be $5,000 per occurrence.
3.
Professional liability insurance affording limits of liability of $1,000,000 per
claim/$1,000,000 aggregate.
The contractor shall maintain the appropriate professional liability, affording limits
of liability of $500,000 each claim and $1,000,000 aggregate for damages
sustained by reason of or in the course of operations under the contract, whether
occurring by reason of acts, errors or omissions of the contractor.
4.
C.
Community Transit reserves the right to require higher limits of coverage for any
and/or all coverage required based upon the scope of project. In such event, the
contractor shall maintain such higher limits for the occurrence.
Community Transit reserves and retains its rights of subrogation.
Community Transit shall further have the right, at its election and expense to pursue
collection and recovery from any and all responsible third parties. The Contractor shall
cooperate with Community Transit in such recovery and collection, and shall make its
records and personnel available.
As to any accident or incident to which this paragraph is applicable, any and all sums so
recovered by Community Transit, as provided hereunder, after deduction only of court
costs, shall be reimbursed to the Contractor. The pendency of any collection efforts
against third parties, including litigation, shall in no way delay or diminish the obligation
of the Contractor to promptly remit the sums due to the Authority under the provisions of
this Paragraph.
D.
The Contractor shall not commence work under this Contract nor shall the Contractor
allow any subcontractor to commence work until it has obtained all insurance required
under this article and such insurance has been approved by Community Transit.