Download Section 1 - Community Transit
Transcript
REQUEST FOR PROPOSALS - RFP #50-07 ADVANCED PUBLIC TRANSPORTATION SYSTEM (APTS) PROCUREMENT SECTION 3.0 - PAGE 8 Explosions, Collapse and Underground Hazards (Where Applicable) Products/Completed Operations Contractual Liability Broad Form Property Damage Independent Contractors Personal Injury/Advertising Liability Stop Gap Liability ($1,000,000 per person/$1,000,000 per occurrence) Profession Services, Errors and Omissions ($1,000,000 per occurrence) 2. Comprehensive auto liability in the amount of $1,000,000 per occurrence limit which provides the following coverages: Owned Vehicles Nonowned Vehicles Hired Vehicles Deductibles and Self Insured retainers, if any, shall be identified in the Proposal. All deductible payments are the responsibility of Contractor. The minimum deductible shall be $5,000 per occurrence. 3. Professional liability insurance affording limits of liability of $1,000,000 per claim/$1,000,000 aggregate. The contractor shall maintain the appropriate professional liability, affording limits of liability of $500,000 each claim and $1,000,000 aggregate for damages sustained by reason of or in the course of operations under the contract, whether occurring by reason of acts, errors or omissions of the contractor. 4. C. Community Transit reserves the right to require higher limits of coverage for any and/or all coverage required based upon the scope of project. In such event, the contractor shall maintain such higher limits for the occurrence. Community Transit reserves and retains its rights of subrogation. Community Transit shall further have the right, at its election and expense to pursue collection and recovery from any and all responsible third parties. The Contractor shall cooperate with Community Transit in such recovery and collection, and shall make its records and personnel available. As to any accident or incident to which this paragraph is applicable, any and all sums so recovered by Community Transit, as provided hereunder, after deduction only of court costs, shall be reimbursed to the Contractor. The pendency of any collection efforts against third parties, including litigation, shall in no way delay or diminish the obligation of the Contractor to promptly remit the sums due to the Authority under the provisions of this Paragraph. D. The Contractor shall not commence work under this Contract nor shall the Contractor allow any subcontractor to commence work until it has obtained all insurance required under this article and such insurance has been approved by Community Transit.