Dependency Parameter Dialog (Predecessor is a Rollup Element)
Item
Predecessor
Description
Predecessor's Activity
Select the predecessor element's software development activity on
which the dependency will be based.
A Schedule Dependency involves two work elements: the dependent
work element, and the predecessor, on which the dependent element's
schedule is based.
Select the predecessor work element from the drop-down list. The list
will include all program-level and rollup-level work elements in the project
other than the dependent work element and any work elements which
depend on it, either directly or indirectly.
Note: This means that if selection of a work element as a predecessor
would cause a circular dependency (so that Program A depended on
Program B, which depended on Program C, which depended in turn on
Program A, for example), that work element will not be listed.