STP 9-27E14-SM-TG
Align the Boresight Collimator
093-27E-1538
Conditions: Perform this task given the following: DA Form 2407, DA Pam 738-750, Land Combat
Electronic Missile System Repairer with Guided Missile Maintenance Tool Kit, TS-3784/TAS boresight
collimator test set or AN/PAM-2, SU-93/TAS, SU-93A/TAS boresight collimator, TM 9-5855-286-14, TM 95855-1286-14, TM 9-5855-585-24.
Standards: Alignment procedures on the SU-93/TAS, SU-93A/TAS boresight collimator were performed
and safety precautions observed according to TM 9-5855-286-14 and 9-5855-1286-14. Tools were used
according to TM 9-243. Maintenance forms were completed according to DA Pam 738-750.
Performance Measures
GO
NO GO
1. Prepared the Boresight Collimator test set for testing.
——
——
2. Performed SU-93/TAS, SU-93A/TAS boresight collimator alignment procedures.
——
——
3. Performed SU-93/TAS, SU-93A/TAS boresight collimator purging procedures.
——
——
4. Completed maintenance forms.
This alignment procedure includes both Boresight Collimator Test sets, however only
one is required to complete the individual task.
——
——
Evaluation Guidance: Score the soldier Go if all performance measures are passed. Score the soldier
no-go if any performance measure is failed. If the soldier fails any performance measure, show what was
done wrong and how to do it correctly.
References
Required
DA PAM 738-750
TM 9-5855-1286-14
TM 9-5855-286-14
TM 9-5855-885-24
Related
3 - 37