Download Model 700 GC
Transcript
3-64 3.6 INSTALLATION AND SETUP MODEL 700 SYSTEM STARTUP To perform system start-up, 1. For system startup, run an analysis of the calibration gas. (a) If equipped with an optional stream switching board, ensure that the stream switch for the calibration stream is set to AUTO. Otherwise, ensure that the calibration gas supply is turned on and set to the correct pressure (25 to 30 PSIG). (b) Using the MON2000 software, run a single stream analysis on the calibration stream. Once proper operation of the GC is verified, halt the analysis. Use the Control > Calibration and Control > Halt menu paths; see Sections 4.3 and 4.4 in the MON2000 Software for Gas Chromatographs User Manual (P/N 3-9000-522) for more information. 2. Start Auto Sequence of the line gas stream(s). Use the Control > Auto Sequence menu path; see Section 4.1 in the MON2000 Software for Gas Chromatographs User Manual (P/N 3-9000-522) for more information. The GC will begin the Auto Sequence analysis mode. System Startup JULY 2007