Commissioning a Project
7.5 Transfer
Procedure
Proceed as follows:
1. On the configuration computer, select the "Transfer settings" command in the menu
"Project > Transfer" in WinCC flexible.
The "Select devices for transfer" dialog opens.
2. Select the HMI device in the left area of the dialog.
3. Select the type of connection between the HMI device and the configuration computer.
Set the connection parameters.
4. Set the transfer parameters in the right area of the dialog.
5. If you wish to transfer the compressed project file together with the runtime project to the
HMI device:
Select the "Activate Upload" check box.
6. Start transfer in WinCC flexible with "Transfer".
The configuration computer checks the connection to the HMI device. The HMI device
ends the current project and automatically switches to "Transfer" mode The project is
transferred to the HMI device. If the connection is not available or is defective, an error
message is displayed on the configuration computer.
Result
When the transfer is completed successfully, the project can be found on the HMI device.
The transferred project is then started automatically.
See also
Data Transmission Options (Page 7-3)
Configuring the Data Channel (Page 6-33)
Operating Modes (Page 7-2)
Overview (Page 7-4)
7.5.4
Testing a Project
Introduction
There are two options to test a project:
• Test the project on the configuration PC
You can test a project at a configuration PC, using a simulator. For detailed information,
refer to the "WinCC flexible" user manual and to the WinCC flexible Online Help.
• Offline testing of the project on the HMI device
Offline testing means that communication between the HMI device and PLC is down
while the test is being carried out.